Schedule Blackout Dates

Reference:

Schedule blackout dates are those dates on which schedules will not run and cannot be set to run. As a ReportCaster user, you can view schedule blackout dates that have been set for all users (global dates) and those set for the groups to which you belong. Only ReportCaster administrators and Managed Reporting Group administrators can define, update, and delete schedule blackout dates.

To view schedule blackout dates, click the Blackout Dates option in the ReportCaster HTML User Interface. The Schedule Blackout Dates interface opens to a calendar of the current year. The group drop-down list in the top left corner provides a list of groups to which you belong and includes a Global selection. This interface initially opens to the Global group and global blackout dates shaded in gray. An example of the Schedule Blackout Dates interface is shown in the following image.

Schedule Blackout Dates interface

To view the schedule blackout dates for a particular group, select that group from the drop‑down list. The calendar refreshes and in addition to the global blackout dates, it displays the group blackout dates in yellow. The following image shows a partial calendar of Schedule Blackout Dates interface for a selected group. For the month of April, it shows group blackout dates on the 23rd and 24th, and global blackout dates on the 25th through the 27th. Schedules cannot be run or set to run on these dates.

partial calendar of Schedule Blackout Dates for a selected group

You can change the year using the arrows at the top right corner of the screen. Click Refresh to load the latest blackout dates. Dates only appear as available or unavailable.

Click Close to exit the HTML User Interface.


Top of page

x
Reference: Schedule Behavior for Blackout Dates

Blackout dates are enforced during schedule creation and at run time: