About Tasks

In this section:

How to:

Reference:

When creating a schedule, you must create a Task to be distributed by ReportCaster. If you are scheduling a report from Dashboard, the task that appears in the schedule is that report. You then have the option to add more tasks, or pre-processing and post-processing procedures to the schedule. The task types are:

When you access the Scheduling tool by right-clicking a Standard Report or My Report from the Dashboard, the Task tab options are predefined with the selected report. You can complete the available task options, such as defining parameter values, and selecting whether or not to burst the report.

The following image shows an example of a predefined Task tab when the Scheduling tool is accessed from Dashboard.

To create a Task:

  1. From the Task Type drop-down list, select the type of task you want to create.
  2. In the Task Name field, type a descriptive name for the task.
  3. Depending on the type of task you are creating, provide the appropriate parameters. For example, provide the FTP server name, FTP user, the file name, the transfer file type, and the name to save the file as on the FTP site.
  4. If applicable, select report parameters, the report format, and whether or not the report is burst.
  5. If applicable, add pre-processing and post-processing procedures to the scheduled job.
  6. Click Save.

Top of page

x
WF Server Procedure Task Options

The options available when you select the WF Server Procedure Task Type are:


Top of page

x
Standard Reports and My Reports Task Options

The options available when you select either Standard Reports or My Reports Task Type are:


Top of page

x
URL Task Options

The options available when you select the URL Task Type are:


Top of page

x
File Task Options

The options available when you select the File Task Type are:


Top of page

x
FTP Task Options

The options available when you select the FTP or SFTP Task Type are:


Top of page

x
Procedure: How to Schedule Pre-Processing and Post-Processing Procedures

If you are scheduling a report Task that is a WF Server Procedure, Standard Report, or My Report, you can schedule a maximum of two pre-processing and post-processing procedures. The pre-processing and post-processing procedures that you schedule must reside on the WebFOCUS Reporting Server.

To schedule pre-processing and post-processing procedures for a Task:

  1. Click Advanced Procedure. The Advanced Procedures window opens, as shown in the following image.

  2. Select the following information:
    1. Pre-processing Procedures:

      First. From the drop-down list, select the first pre-processing procedure. ReportCaster will run this procedure immediately preceding the scheduled Task.

      Second. From the drop-down list, select the second pre-processing procedure. ReportCaster will run this procedure immediately after the first pre-processing procedure, but before the scheduled Task.

    2. Post-processing Procedures:

      First. From the drop-down list, select the first post-processing procedure. ReportCaster will run this procedure immediately following the scheduled Task.

      Second. From the drop-down list, select the second post-processing procedure. ReportCaster will run this procedure immediately after the first post-processing procedure.

  3. Click OK to return to the Task tab.

Top of page

x
Reference: Selecting a Report Format

Use the following guidelines when selecting a format:


WebFOCUS