The Scheduler reports folder include two reports:
The Scheduler Log report is a drill-down report, which allows you to click entries to display details about the individual flows.
The Scheduler Log report displays the date/time when scheduled flows were submitted, as well as their Job IDs.
The Log and Statistics window opens.
The report of scheduled flows opens.
Note: Double-clicking a Link to log row will display the log for that flow.
Scheduler Log reports provide the information listed and described in the following table:
Column |
Format |
Function |
---|---|---|
SUBMIT_DATE_TIME |
Alpha 20 |
Submit date and time for flow. |
APPNAME |
Alpha 64 |
Flow application directory |
REQUEST |
Alpha 64 |
Flow name. |
LOG |
Alpha 64 |
Link to the flow log. |
The Scheduled Events reports provides information about what time flows are scheduled to run on a particular day.
The Scheduled Events window opens.
Note: The date-field drop-down menu launches a calendar for selecting dates. The time-field scroll buttons allow you change the highlighted section of the time. For example, you can change the hour, minute, or second.
The report opens in the workspace, as shown in the following image.
The Scheduler Agents report provides information about every scheduled flow and the next and last runs.
In the navigation pane, right-click an application directory, select Schedule and E-mail, and then click Scheduler Agents.
The Scheduler Agents report opens, as shown in the following image.
Scheduled Events reports provide the information listed and described in the following table:
Column |
Format |
Function |
---|---|---|
ID | ||
State |
The scheduling state of the flow. | |
Application |
Alpha 18 |
Flow application directory. |
Procedure |
Alpha 32 |
Flow name. |
User ID |
Alpha 32 |
Flow author. |
Schedule Type |
How often the flow is run. | |
Last Run Time |
The last time the flow ran. | |
Next Run Time |
Time flow is scheduled to run. |
To access the DM Scheduled Events window shown in the following image, right-click Scheduler and click Scheduled Events in the Workspace folder in the navigation pane, , or right-click an application directory, select View, and then click Scheduled Events.
The DM Scheduled Events window has the following fields and options:
Start of the specific time period for generating this report.
Note: The date-field drop-down menu launches a calendar for selecting dates. The time-field scroll buttons allow you change the highlighted section of the time. For example, you can change the hour, minute, or second.